Explainer
Transmission lines and interconnection queues explained
High-voltage transmission lines move power over long distances because higher voltage makes that cheaper and more efficient, and the Lower 48 grid is split into three main interconnections.[1][2] New plants must apply to connect through interconnection queues, which FERC found had grown past 2,000 GW with average waits of about five years by 2022, prompting its Order No. 2023 reforms.[3][4] Lawrence Berkeley National Laboratory reported 2,061 GW still queued at the end of 2025, down 10% in a year, while a July 2026 DOE draft study found a pressing need for more transmission because of load growth.[5][6]
This explainer covers what transmission does, how new generators connect to the grid, the federal rules that govern both, and the latest queue data. It does not cover local distribution lines or retail rates; see the power grid and electricity prices explainers for those.
What transmission does
Power plants are often far from the cities that use their electricity. High-voltage transmission lines carry that power long distances, because higher voltage makes long-distance transmission more efficient and cheaper.[1] The US has thousands of miles of these big lines and millions of miles of smaller local ones.[1]
The Lower 48 grid has three main interconnections: the Eastern, the Western and ERCOT, which covers most of Texas.[2] Transmission constraints are one reason wholesale prices differ by location.[7]
Why more transmission is needed
DOE released a draft National Transmission Needs Study on 9 July 2026. It finds a pressing need for more transmission because of load growth, and that most congestion is concentrated in 5% of hours.[6] The draft says interregional lines improve reliability and resilience and help meet demand growth in at-risk areas; the study meets a legal requirement to assess transmission constraints at least every three years.[8] The study names hyperscale AI data centres and domestic manufacturing among the sources of that load growth; see AI data centres and power.[6]
FERC Order No. 1920, effective 12 August 2024, requires transmission providers to carry out long-term regional planning using scenarios, weigh benefits over at least 20 years, and consider alternative transmission technologies.[9]
How interconnection queues work
Proposed power plants and storage projects must apply to connect to the transmission system through interconnection queues. Lawrence Berkeley National Laboratory (LBNL) notes that many will never be built, because joining a queue is only one of many development steps.[10]
Think of it as a waiting list for connecting to the grid. By 2022 the list had grown to more than 2,000 GW, with waits of around five years.[3]
FERC found that between 2021 and 2022 average waits rose from roughly four to five years while queued capacity grew from 1,400 GW to more than 2,000 GW.[3] Order No. 2023, effective 6 November 2023, replaced serial studies with a first-ready, first-served cluster study process.[4] It also requires study and commercial readiness deposits, proof of site control at application, and penalties for withdrawing from the queue.[11]
What the latest queue data show
LBNL reported that 2,061 GW of generation and storage was actively seeking interconnection at the end of 2025, down 10% from 2024 and from a peak of nearly 2,600 GW at the end of 2023; more than 750 GW was withdrawn in 2025.[5] Queued natural gas capacity rose 86% to 253 GW while solar (773 GW), storage (749 GW) and wind (220 GW) all fell. The non-ISO West (567 GW) and ERCOT (408 GW) had the most queued capacity.[12] LBNL also found that 536 GW already had a draft or executed interconnection agreement, and CAISO, ERCOT, SPP and MISO each signed a record capacity of agreements in 2025.[13] These figures are LBNL’s, as summarised by the American Public Power Association.[5]
Two large grid operators, PJM and ERCOT, have their own pages.
Read next: how wholesale electricity markets work, for how transmission limits turn into price differences.
See how electricity markets work and how the power grid works.
Read next
ERCOT (Electric Reliability Council of Texas)
ERCOT runs the Texas power grid for 27 million customers. Why it stands apart from other US grids, its fuel mix, the 2021 freeze and the data centre queue.
More in Energy and climate
Questions readers ask
Why does electricity travel on high-voltage lines?
Higher voltage makes long-distance transmission more efficient and less expensive.[1]
What are the three US grid interconnections?
The Eastern Interconnection, the Western Interconnection and ERCOT, which covers most of Texas.[2]
What is an interconnection queue?
The line that proposed power plants and storage projects join when they apply to connect to the transmission system. Many projects in it are never built, because joining the queue is only one of many development steps.[10]
How big is the interconnection queue?
LBNL reported 2,061 GW of generation and storage actively seeking interconnection at the end of 2025, down 10% from 2024 and from a peak of nearly 2,600 GW at the end of 2023.[5]
What did FERC Order No. 2023 change?
It replaced serial studies with a first-ready, first-served cluster study process, and required deposits, proof of site control and penalties for withdrawing, to clear queue backlogs.[4][11]
What is FERC Order No. 1920?
A 2024 rule requiring long-term regional transmission planning that uses scenarios, weighs benefits over at least 20 years and considers alternative transmission technologies.[9]
What kinds of projects are in the queue?
In LBNL's end-2025 data, solar (773 GW) and storage (749 GW) were the largest, but both fell, while natural gas rose 86% to 253 GW.[12]
Sources
· 13 claims from 5 publishers
Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.
- [1]
High-voltage lines carry power over long distances because higher voltage makes long-distance transmission more efficient and cheaper; the US grid has thousands of miles of high-voltage lines and millions of miles of low-voltage lines. confirmedas of 2026-11-07
- Electricity explained: Delivery to consumers · US Energy Information Administration · Primary source · Section: Delivering electricity (retrieved 2026-11-07)
- Electricity explained: Delivery to consumers · US Energy Information Administration · Primary source · Opening section (retrieved 2026-11-07)
- [2]
The grid in the Lower 48 states has three main interconnections, the Eastern, the Western and ERCOT, which covers most of Texas. confirmedas of 2026-11-07
- Electricity explained: Delivery to consumers · US Energy Information Administration · Primary source · Section: Interconnections (retrieved 2026-11-07)
- Electricity explained: Delivery to consumers · US Energy Information Administration · Primary source · Section: Interconnections (retrieved 2026-11-07)
- [3]
FERC found that between 2021 and 2022 average waits in interconnection queues rose from roughly four to five years while total queued capacity grew from 1,400 GW to more than 2,000 GW. confirmedas of 2023-09-06
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Order No. 2023, paragraph 1012 (retrieved 2026-11-07)
- [4]
FERC Order No. 2023, effective 6 November 2023, reformed generator interconnection rules to address queue backlogs, replacing serial studies with a first-ready, first-served cluster study process. confirmedas of 2023-09-06
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Summary (retrieved 2026-11-07)
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Dates (retrieved 2026-11-07)
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Paragraph 4 (retrieved 2026-11-07)
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Paragraph 5 (retrieved 2026-11-07)
- [5]
LBNL reported that 2,061 GW of generation and storage was actively seeking interconnection at the end of 2025, down 10% from 2024 and from a peak of nearly 2,600 GW at the end of 2023, with more than 750 GW withdrawn in 2025. reportedas of 2026-07-01
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · First paragraph (retrieved 2026-11-07)
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Second paragraph (retrieved 2026-11-07)
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Third paragraph; the source prints >750 GW (more than 750 GW) (retrieved 2026-11-07)
- [6]
DOE released a draft National Transmission Needs Study on 9 July 2026, finding a pressing need for more transmission because of load growth, driven in part by hyperscale AI data centres and domestic manufacturing, and that most congestion is concentrated in 5% of hours. confirmedas of 2026-11-07
- National Transmission Needs Study · US Department of Energy, Grid Deployment Office · Primary source · Study overview (retrieved 2026-11-07)
- National Transmission Needs Study · US Department of Energy, Grid Deployment Office · Primary source · Key findings, 1 (retrieved 2026-11-07)
- National Transmission Needs Study · US Department of Energy, Grid Deployment Office · Primary source · Introduction (retrieved 2026-11-07)
- National Transmission Needs Study · US Department of Energy, Grid Deployment Office · Primary source · Key findings, 1 (retrieved 2026-11-07)
- [7]
With no transmission limits or losses every location would have the same price; prices differ because constraints stop the next-cheapest megawatt from reaching every location. confirmedas of 2026-11-07
- FAQs: Locational Marginal Pricing · ISO New England · Primary source · Why do LMPs differ? (retrieved 2026-11-07)
- FAQs: Locational Marginal Pricing · ISO New England · Primary source · Why do LMPs differ? (retrieved 2026-11-07)
- [8]
The draft study says interregional transmission improves reliability and resilience and helps meet demand growth, and the study meets a legal requirement to assess transmission constraints at least every three years. confirmedas of 2026-11-07
- National Transmission Needs Study · US Department of Energy, Grid Deployment Office · Primary source · Key findings, 2 (retrieved 2026-11-07)
- National Transmission Needs Study · US Department of Energy, Grid Deployment Office · Primary source · Study overview (retrieved 2026-11-07)
- [9]
FERC Order No. 1920, effective 12 August 2024, requires transmission providers to conduct long-term regional transmission planning using scenarios, weigh benefits over at least 20 years, and consider alternative transmission technologies. confirmedas of 2024-06-11
- Building for the Future Through Electric Regional Transmission Planning and Cost Allocation (Order No. 1920) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2024-06-11 · Summary (retrieved 2026-11-07)
- Building for the Future Through Electric Regional Transmission Planning and Cost Allocation (Order No. 1920) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2024-06-11 · Paragraph 2 (retrieved 2026-11-07)
- Building for the Future Through Electric Regional Transmission Planning and Cost Allocation (Order No. 1920) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2024-06-11 · Paragraph 3 (retrieved 2026-11-07)
- Building for the Future Through Electric Regional Transmission Planning and Cost Allocation (Order No. 1920) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2024-06-11 · Summary (retrieved 2026-11-07)
- Building for the Future Through Electric Regional Transmission Planning and Cost Allocation (Order No. 1920) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2024-06-11 · Dates (retrieved 2026-11-07)
- [10]
Lawrence Berkeley National Laboratory notes that proposed large generation and storage projects must apply to connect to the transmission system through interconnection queues, and that many will never be built, because joining a queue is only one of many development steps. reportedas of 2026-07-01
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Quoting LBNL (retrieved 2026-11-07)
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Quoting LBNL (retrieved 2026-11-07)
- [11]
Order No. 2023 requires developers to pay study and commercial readiness deposits, show site control when they apply, and face penalties for withdrawing from the queue. confirmedas of 2023-09-06
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Paragraph 5 (retrieved 2026-11-07)
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Paragraph 5 (retrieved 2026-11-07)
- Improvements to Generator Interconnection Procedures and Agreements (Order No. 2023) · Federal Register (Federal Energy Regulatory Commission) · Primary source · 2023-09-06 · Paragraph 5 (retrieved 2026-11-07)
- [12]
In LBNL's end-2025 data, queued natural gas capacity rose 86% to 253 GW while solar (773 GW), storage (749 GW) and wind (220 GW) all fell; the non-ISO West (567 GW) and ERCOT (408 GW) had the most queued capacity. reportedas of 2026-07-01
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Body (retrieved 2026-11-07)
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Body (retrieved 2026-11-07)
- [13]
LBNL found that 536 GW of queued capacity already had a draft or executed interconnection agreement, and CAISO, ERCOT, SPP and MISO each signed a record capacity of agreements in 2025. reportedas of 2026-07-01
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Body (retrieved 2026-11-07)
- Backlog of power plants seeking transmission grid connection eased somewhat in 2025, LBNL · American Public Power Association · Secondary source · 2026-07-01 · Body (retrieved 2026-11-07)
Revision history (2)
- Marked the LBNL queue claim, cited through APPA, as reported.
- Page created.
Created Nov 7, 2026. Last reviewed by an editor on Nov 8, 2026. Next scheduled review: Feb 7, 2027.