    How the power grid works

    The power grid is the network of power plants, substations, transformers and lines that carries electricity to consumers, and its operators must keep supply matched to demand at every moment.[1][2] In the US, more than 2,000 GW of proposed generation and storage was waiting to connect at the end of 2025, while the IEA expects data centres to drive nearly half of US demand growth to 2030.[3][4]

    Editor reviewedUpdated Explainer34 claims · 91% primaryEnergy and climate, Science
    Reading level: 2 passages differ; the rest is the same for everyone.

    This explainer covers how a power grid moves and balances electricity, who operates it in the US and Great Britain, and why connecting new power plants and data centres has become a bottleneck. For the sources that feed the grid, read the companion pages on solar and wind power.

    From power plant to plug

    The grid is made of substations, transformers and power lines that connect electricity producers to consumers.[1] Power plants send electricity over high-voltage transmission lines because high voltages make long-distance delivery cheaper and more efficient.[5] Transformers then step the voltage down so local distribution lines can deliver it safely to homes and businesses.[6] Whoever generates the power, it is usually the local utility that runs the wires to your building.[7]

    Electricity is generated, stepped up at substation transformers for bulk transmission, and stepped down again for distribution.[6][5] The US network spans thousands of miles of high-voltage lines and millions of miles of low-voltage lines, linking thousands of power plants to hundreds of millions of customers.[8] It grew out of more than 4,000 isolated utilities in the early 20th century, which interconnected to share large plants and reduce the reserve capacity each one had to hold.[9]

    In 2025, US utility-scale plants generated about 4.43 trillion kWh. Natural gas was the largest source at about 41%, followed by renewables at about 24%, nuclear at about 18% and coal at about 17%.[10] A plant’s capacity is the most it can produce, while its capacity factor is the share of that maximum it actually delivers over time.[11] In 2025, US nuclear plants ran at an average capacity factor of 91.1%, against 33.8% for wind and 24.0% for solar PV.[12]

    Keeping supply and demand in balance

    The grid has very little room for error: the amount of electricity going in must match the amount being used.[2] If the two drift apart, blackouts can follow, so organisations called balancing authorities watch the balance continuously.[2][13]

    The lower 48 US states have three main interconnections, Eastern, Western and ERCOT, which mostly operate independently and rarely exchange power.[14] Within them, balancing authorities manage day-to-day operations, and every US regional transmission organization also acts as one.[13] Wind and solar output varies with the weather, and the IEA expects these variable sources to supply almost 30% of global electricity by 2030, double today’s level, which it says requires much more flexibility and grid investment.[15] It points to rising curtailment and more hours of negative prices around peak solar output as signs that flexibility is lacking, and lists demand response, storage and dispatchable plants as the remedies.[16][17]

    More on storage: how grid-scale storage works.

    Who runs the grid

    Regional transmission organizations (RTOs), also called independent system operators (ISOs), are independent, membership-based non-profits that keep the bulk system reliable and run wholesale markets.[18] They first developed in the 1990s to accommodate a FERC policy that required open access to transmission in order to encourage competitive generation.[19] RTOs dispatch plants by feeding day-ahead and real-time bids into optimisation software, and publish prices for thousands of locations at intervals as short as five minutes.[20] Reliability rules come from the North American Electric Reliability Corporation (NERC), which develops and enforces mandatory standards approved by the Federal Energy Regulatory Commission (FERC).[21]

    In Great Britain, the National Energy System Operator (NESO) took over on 1 October 2024. The government bought the Electricity System Operator from National Grid to form it as a publicly owned body, with responsibilities across electricity, gas and hydrogen.[22] The UK government says NESO will help connect new generation projects to the grid.[23]

    The interconnection queue

    Every large new plant or battery must apply to connect to the transmission system through an interconnection queue.[24] Lawrence Berkeley National Laboratory (LBNL) counted 2,061 GW of generation and storage in US queues at the end of 2025. That was down 10% from a year earlier and below a peak of nearly 2,600 GW at the end of 2023.[3] Solar (773 GW) and storage (749 GW) still dominated, but natural gas in the queues rose 86% to 253 GW.[25]

    Many queued projects are never built, because a queue position is only one step alongside land, permits, buyers and financing.[24] Of the capacity that applied between 2000 and 2020, only 13% had come online by the end of 2025, and 75% had withdrawn.[26] In 2025 the median wait from request to signed interconnection agreement was well over three years, and reaching commercial operation took more than five.[27] FERC adopted interconnection reforms in 2023 that took effect in most regions in 2024. LBNL says these reforms and market conditions may have contributed to more than 750 GW of withdrawals in 2025.[28] Developers still planned a record 86 GW of new US capacity for 2026, mostly solar, batteries and wind.[29]

    Data centres and new demand

    The IEA projects that data centres will account for nearly half of US electricity demand growth between 2025 and 2030.[4] Worldwide, it expects data centre electricity use to roughly double from 485 TWh in 2025 to 950 TWh in 2030.[30] The IEA says new transmission lines take four to eight years in advanced economies, and that waiting times for transformers and cables doubled in the three years to 2025.[31] It estimated in 2025 that about 20% of planned data centre projects could be delayed unless these grid risks are addressed.[32] In October 2026 the EIA forecast 2026 wholesale prices in the PJM region 41% above 2025, the largest rise of any region it tracks.[33] The EIA also lists siting new lines, sharing their costs across states and reaching distant wind and solar resources as long-standing grid challenges.[34]

    For more on how AI is changing electricity demand, read the data centre explainer and the live power tracker. Firm low-carbon supply options are covered in the small modular reactor explainer.

    Next in the crash course

    More in Energy and climate

    Developing in Science & Energy

    Questions readers ask

    Why does electricity travel at high voltage?

    Higher voltages make long-distance transmission more efficient and less expensive. Transformers at substations step the voltage up for transmission lines and back down for the local distribution lines that serve homes and businesses.[5][6]

    What happens if supply and demand fall out of balance?

    Supply must match demand for the grid to stay stable. If they fall out of balance, local or even widespread blackouts can happen, which is why balancing authorities manage this balance continuously.[2][13]

    What is an ISO or RTO?

    Regional transmission organizations are independent, membership-based non-profits that run bulk power systems and wholesale markets. They dispatch plants using day-ahead and real-time bids and publish prices for thousands of locations as often as every five minutes.[18][20]

    Who sets reliability rules for the North American grid?

    The North American Electric Reliability Corporation (NERC) develops and enforces mandatory reliability standards, which the Federal Energy Regulatory Commission approves.[21]

    Who runs the grid in Great Britain?

    The National Energy System Operator (NESO), a publicly owned body established on 1 October 2024 after the government bought the Electricity System Operator from National Grid.[22]

    What is an interconnection queue?

    It is the line of proposed power plants and storage projects waiting for permission to connect to the transmission system. At the end of 2025, 2,061 GW was in US queues, and historically only 13% of requested capacity has been built.[3][26]

    Sources

    · 34 claims from 7 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      The electricity grid is the system of substations, transformers and power lines that carries electricity from power plants to consumers. confirmedas of 2026-11-07

    2. [2]

      To keep the grid stable, the amount of electricity supplied must match demand at all times; if they fall out of balance, local or widespread blackouts can happen. confirmedas of 2026-11-07

    3. [3]

      Lawrence Berkeley National Laboratory reported that more than 2,060 GW of generation and storage capacity (1,312 GW of generation and about 749 GW of storage) was actively seeking US grid interconnection at the end of 2025, a 10% decrease from a year earlier; the American Public Power Association's summary of the report gives 2,061 GW and a peak of nearly 2,600 GW at the end of 2023. confirmedas of 2026-11-14

    4. [4]

      The IEA projects that data centres account for nearly half of US electricity demand growth between 2025 and 2030. confirmedas of 2025-04-10· forecast

    5. [5]

      High-voltage transmission lines carry electricity over long distances because higher voltages make long-distance transmission more efficient and less expensive. confirmedas of 2026-11-07

    6. [6]

      Transformers at substations step voltage up for long-distance transmission and step it down for the distribution lines that serve homes and businesses. confirmedas of 2026-11-07

    7. [7]

      Whatever the source of the electricity, local utilities operate the distribution system that connects homes and businesses to the grid. confirmedas of 2026-11-07

    8. [8]

      The US grid is made up of thousands of miles of high-voltage power lines and millions of miles of low-voltage lines, connecting thousands of power plants to hundreds of millions of customers. confirmedas of 2026-11-07

    9. [9]

      At the start of the 20th century more than 4,000 isolated electric utilities operated in the US; they later linked their transmission systems to share large power plants and reduce the spare capacity each needed. confirmedas of 2026-11-07

    10. [10]

      US utility-scale power plants generated about 4.43 trillion kWh in 2025; natural gas supplied about 41%, renewables about 24%, nuclear about 18% and coal about 17%. confirmedas of 2026-11-07

    11. [11]

      A generator's capacity is its maximum output, while its capacity factor is the ratio of what it actually produced over a period to the most it could have produced. confirmedas of 2026-11-07

    12. [12]

      In 2025, US utility-scale solar photovoltaic plants had an average capacity factor of 24.0%, wind 33.8% and nuclear 91.1%, according to EIA data. confirmedas of 2026-11-07

    13. [13]

      Day-to-day operation within each region is managed by balancing authorities, which keep supply matched to demand; most are utilities, and all US regional transmission organizations also act as balancing authorities. confirmedas of 2026-11-07

    14. [14]

      The grid in the lower 48 US states has three main interconnections, Eastern, Western and ERCOT (most of Texas), which mostly operate independently and rarely transfer electricity among them. confirmedas of 2026-11-07

    15. [15]

      The IEA expects variable renewables (wind and solar PV) to generate almost 30% of global electricity by 2030, double today's level, which it says calls for a rapid increase in power system flexibility and grid investment. confirmedas of 2025-10-07· forecast

    16. [16]

      The IEA, which defines technical curtailment as dispatching down renewable output for network or system reasons, reports rising curtailment of wind and solar in markets including China, Germany, Brazil, Chile, the UK and Ireland, and a surge in hours with negative power prices coinciding with peak solar output. confirmedas of 2025-10-07

    17. [17]

      The IEA says curtailment and negative prices signal a lack of flexibility, and that demand-side flexibility, storage and dispatchable power plants will increasingly be needed to integrate wind and solar. confirmedas of 2025-10-07

    18. [18]

      Regional transmission organizations (RTOs) are independent, membership-based, non-profit organizations that run bulk power systems, ensure reliability and match supply and demand bids in wholesale electricity markets. confirmedas of 2026-11-07

    19. [19]

      RTOs first developed in the 1990s to accommodate a FERC policy that encouraged competitive generation by requiring open access to transmission. confirmedas of 2026-11-07

    20. [20]

      RTOs dispatch power plants by feeding day-ahead and real-time bids into optimisation software and publish prices for thousands of locations at intervals as short as five minutes. confirmedas of 2026-11-07

    21. [21]

      The North American Electric Reliability Corporation (NERC) develops and enforces mandatory grid reliability standards, which are approved by the Federal Energy Regulatory Commission (FERC). confirmedas of 2026-11-07

    22. [22]

      Great Britain's National Energy System Operator (NESO) was established on 1 October 2024 as a publicly owned body, taking on all the functions of the previous Electricity System Operator after the government bought it from National Grid, along with responsibilities across gas and hydrogen. confirmedas of 2026-11-07

    23. [23]

      The UK government says NESO will help connect new generation projects to the electricity grid. confirmedas of 2026-11-07

    24. [24]

      Proposed large generation and storage projects must apply to connect to the US transmission system through interconnection queues, and LBNL notes that many projects in the queues are never built, because joining a queue is only one step and projects also need land agreements, permits, buyers, suppliers and financing. reportedas of 2026-07-01

    25. [25]

      According to LBNL, natural gas capacity in US interconnection queues rose 86% in 2025 to 253 GW, while solar (773 GW), storage (749 GW) and wind (220 GW) all fell. confirmedas of 2026-11-14

    26. [26]

      LBNL found that of the capacity that requested interconnection from 2000 to 2020, just 13% had come online by the end of 2025 and 75% had withdrawn. confirmedas of 2026-11-14

    27. [27]

      LBNL reported that in 2025 the median time from an interconnection request to a signed interconnection agreement was well over three years, and the time to commercial operation exceeded five years in regions with data. reportedas of 2026-07-01

    28. [28]

      FERC adopted major interconnection reforms in 2023 that took effect in most regions in 2024, and LBNL says reforms and market conditions may have contributed to more than 750 GW of requests being withdrawn in 2025. reportedas of 2026-07-01

    29. [29]

      US developers planned a record 86 GW of new utility-scale generating capacity for 2026, of which solar made up 51%, battery storage 28% and wind 14%; 53 GW was added in 2025. confirmedas of 2026-02-20

    30. [30]

      The IEA's April 2026 projection has data centre electricity use roughly doubling from 485 TWh in 2025 to 950 TWh in 2030, about 3% of global electricity demand. confirmedas of 2026-04-16· forecast

    31. [31]

      The IEA says new transmission lines take four to eight years in advanced economies, and wait times for transformers and cables doubled in the three years to 2025. confirmedas of 2025-04-10

    32. [32]

      The IEA estimated in 2025 that around 20% of planned data centre projects could face delays unless grid risks are addressed. confirmedas of 2025-04-10· forecast

    33. [33]

      In its October 2026 Short-Term Energy Outlook, the EIA forecast 2026 wholesale electricity prices in the PJM region 41% higher than in 2025, the largest increase of any region it tracks. confirmedas of 2026-10-06· forecast

    34. [34]

      The EIA lists siting new transmission lines, sharing their costs across states, and reaching wind and solar resources far from cities among the challenges in upgrading the US grid. confirmedas of 2026-11-07

    Revision history (1)
    1. Page created.

    Created Nov 7, 2026. Last reviewed by an editor on Nov 8, 2026. Next scheduled review: Feb 7, 2027.