● Developing story
AI data center power tracker: 2026 deals, grid rules and pauses
In 2026 tech companies signed large nuclear and power deals: Meta announced agreements supporting up to 6.6 GW in January, and in October Google contracted 3,590 MW from Constellation, including 890 MW from nuclear uprates.[1][2] Regulators also acted. FERC found grid operators' large-load rules apparently inadequate in June, and Texas paused new data center connections in August pending an audit that ERCOT aims to finish by December 10.[3][4][5]
What we know
- The IEA estimates data centers used about 485 TWh of electricity in 2025 and projects about 950 TWh in 2030[28]
- Gartner forecasts 565 TWh of data center electricity use in 2026, up 26%[7]
- Meta announced nuclear agreements supporting up to 6.6 GW by 2035[1]
- Google contracted 3,590 MW from Constellation, including 890 MW of nuclear uprates[2]
- FERC issued six show cause orders on large-load interconnection on June 18, 2026[3]
- Texas paused new data center connections pending an audit; ERCOT's queue is about 474 GW[4]
- At least 81 US cities and counties had data center moratoriums in August 2026[25]
- GE Vernova expects at least 130 GW of gas equipment under contract by end-2026[14]
What we don't know yet
- How grid operators answer FERC's show cause orders, due in mid-November 2026, and what rules FERC then sets
- How PJM revises its large-load plan after FERC rejected most of it in October 2026, and what curtailment rules states adopt
- How many data center proposals in ERCOT pass the state audit, which ERCOT aims to finish by December 10, 2026, and when connections resume
- Whether New York's pause on new data center approvals leads to permanent development rules, and what they require
- Whether gas turbine and grid equipment makers can expand output fast enough to shorten multi-year lead times
- How much of 2026's announced demand turns into built data centers, given speculative queue requests
This tracker follows power supply, grid rules and local limits for AI data centers in 2026, up to 14 November. It covers mainly the United States, where most deals and rule changes happened. For background, read AI data centers and electricity, explained. For the forecasts, see How much power will AI need?.
Data center electricity use grew 17% in 2025, according to the IEA, and Gartner expects 26% growth in 2026.[6][7]
Nuclear deals
Meta announced agreements with Vistra, TerraPower and Oklo on January 9, 2026. They support up to 6.6 GW of new and existing clean power by 2035, including more output from the Perry, Davis-Besse and Beaver Valley plants.[1] Meta says it pays the full cost of the energy its data centers use.[8]
On October 6, Google and Constellation announced a 20-year agreement for 890 MW from uprates at existing nuclear plants in the PJM grid, with first deliveries expected in 2028. A further 2,700 MW long-term supply deal brings the total to 3,590 MW.[2] Google says the uprates will add 890 MW before the end of 2032. It counts more than 1.5 GW of new US nuclear capacity it has enabled, including the planned restart of Iowa’s Duane Arnold plant.[9] On October 27, Constellation announced a conditional Department of Energy loan of up to $5 billion for uprates. It said its Google and Amazon agreements had led it to invest more than $7 billion to add about 1,080 MW.[10] In November, Constellation said it was also offering “Peak+” contracts that pair existing nuclear output with batteries, demand response or new generation. Its first customer, which it did not name, signed a 20-year, 270 MW agreement.[11]
Gas, turbines and storage
Gas turbine orders rose 70% in 2025, according to the IEA.[12] The IEA’s April report found US developers building onsite gas plants because grid connections are slow. About one-fifth of the projects it tracked had started land clearing or construction.[13] GE Vernova said on October 28 that it expected to end 2026 with at least 130 GW of gas equipment under contract and a backlog above $200 billion. Its chief executive said it continues to develop solutions for utility and data center customers.[14]
In March, a Google–Xcel agreement included a 30 GWh Form Energy iron-air battery, and Crusoe agreed to buy 12 GWh of Form storage for AI data centers.[15][16] More on storage is in the energy storage tracker.
Grid rules and reliability
The Department of Energy directed FERC in October 2025 to set rules for connecting data centers to the transmission grid.[17] On June 18, 2026, FERC issued six show cause orders. They found grid operators’ large-load rules appeared inadequate and named five issues to fix.[3] FERC later extended the deadline for responses to mid-November.[18] Separately, Utility Dive reported that FERC in October largely rejected PJM’s plan for connecting large loads, including an interim service that would have let them connect without matching new capacity if they agreed to be curtailed. FERC found that key parts intruded on state jurisdiction over retail rates and appeared to discriminate against large loads. It approved PJM’s definition of large loads and a registry of them.[19]
NERC issued a Level 3 alert, its highest level, on May 4 after data centers unexpectedly dropped load or swung demand.[20] Texas regulators approved ride-through rules on July 9. ERCOT said it had recorded 28 trips of at least 100 MW since 2023.[21] On July 22, about 3,800 MW of data center load tripped offline in northern Virginia, the largest such event in PJM’s history, according to the grid operator.[22]
Pauses, moratoriums and cost rules
Texas Governor Greg Abbott called on August 3 for an audit of every data center in ERCOT’s queue, pausing new connections. He said requests totalled about 474 GW, around 90% of them data centers.[4] ERCOT aims to audit hundreds of proposals by December 10; about 300 data centers of 75 MW or more are in its Batch Zero study process.[5] Utility Dive reported that New York halted new data center approvals in July for up to a year.[23]
On August 18 Pennsylvania Governor Josh Shapiro signed an order offering faster permits to data centers over 25 MW that bring new power supply and accept cost-responsibility standards.[24] At least 81 US cities and counties had moratoriums on data center development by August.[25] States are also using large-load tariffs. There were 77 pending or in place across 36 states in March.[26] The EIA forecasts 2026 wholesale prices in PJM 41% above 2025.[27]
Timeline
8 confirmed9 reported
reported
Constellation offers hybrid nuclear-plus-capacity contracts[11]
Constellation said it signed a first, unnamed customer for a 20-year, 270 MW "Peak+" agreement.
confirmed
GE Vernova expects 130 GW of gas equipment under contract[14]
confirmed
Constellation wins conditional $5 billion DOE loan for nuclear uprates[10]
reported
FERC rejects most of PJM's large-load connection plan[19]
FERC found that key parts of PJM's interim service framework intruded on state jurisdiction over retail rates. It approved PJM's large-load definition and registry.
confirmed
Google signs 3,590 MW power deal with Constellation[2][9]
confirmed
EIA forecasts 41% higher wholesale power prices in PJM this year[27]
reported
Pennsylvania offers faster permits to data centers that bring new power[24]
reported
Texas governor calls for an audit of data centers in ERCOT's queue, pausing connections[4][5]
reported
About 3,800 MW of data center load trips offline in Virginia[22]
PJM called it the largest such event in its history.
reported
Texas regulators approve ride-through rules for data centers[21]
reported
FERC finds grid operators' large-load rules apparently inadequate[3]
Six show cause orders name five issues, including cost shifts, co-location and services for flexible loads.
reported
NERC issues a Level 3 alert on data center load losses[20]
confirmed
IEA estimates 17% growth in data center power use in 2025[6][28]
The IEA projects roughly a doubling to 950 TWh by 2030.
reported
Large-load tariffs reach 77 across 36 states[26]
The Smart Electric Power Alliance count includes tariffs pending or in place.
confirmed
Form Energy and Crusoe agree 12 GWh of storage for AI data centers[16]
confirmed
Google–Xcel agreement includes a 30 GWh iron-air battery[15]
confirmed
Meta announces nuclear deals supporting up to 6.6 GW[1]
The agreements with Vistra, TerraPower and Oklo include uprates and life extensions at the Perry, Davis-Besse and Beaver Valley plants.
Read next
How much power will AI need? Comparing the forecasts
The IEA, Gartner, Berkeley Lab, EPRI, Goldman Sachs and grid operators disagree on AI's electricity needs. The numbers side by side, and why they differ.
Questions readers ask
What were the biggest AI power deals of 2026?
Meta announced nuclear agreements in January supporting up to 6.6 GW by 2035. In October, Google contracted 3,590 MW from Constellation, including 890 MW from uprates at existing nuclear plants.[1][2]
Has any US state paused data center connections?
Yes. Texas Governor Greg Abbott ordered an audit of data centers in ERCOT's queue on August 3, 2026, pausing new connections, and ERCOT aims to finish by December 10. Utility Dive reported that New York halted new approvals in July for up to a year.[4][5][23]
What did FERC do about data centers in 2026?
On June 18, 2026 FERC issued six show cause orders finding grid operators' large-load interconnection rules appeared inadequate. It later extended their deadline to respond to mid-November. In October, FERC largely rejected PJM's separate plan for connecting large loads, according to Utility Dive.[3][18][19]
Sources
· 28 claims from 11 publishers
Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.
- [1]
On January 9, 2026 Meta announced nuclear agreements with Vistra, TerraPower and Oklo supporting up to 6.6 GW of new and existing clean power by 2035, including uprates and life extensions at the Perry, Davis-Besse and Beaver Valley plants. confirmedas of 2026-01-09
- Meta Announces Nuclear Energy Projects, Unlocking Up to 6.6 GW to Power American Leadership in AI Innovation · Meta · Primary source · 2026-01-09 · Body (retrieved 2026-11-07)
- Meta Announces Nuclear Energy Projects, Unlocking Up to 6.6 GW to Power American Leadership in AI Innovation · Meta · Primary source · 2026-01-09 · Body (retrieved 2026-11-07)
- [2]
On October 6, 2026 Google and Constellation announced a 20-year agreement for 890 MW of new capacity from uprates at existing nuclear plants in PJM, with first deliveries expected in 2028, alongside a long-term supply agreement for another 2,700 MW, for 3,590 MW in total. confirmedas of 2026-10-06
- Why we're backing America's existing nuclear plants · Google · Primary source · 2026-10-06 · First paragraph (retrieved 2026-11-07)
- Google enters massive 3.6-GW power deal with Constellation Energy · CNBC · Secondary source · 2026-10-06 · First paragraph (retrieved 2026-11-07)
- Google enters massive 3.6-GW power deal with Constellation Energy · CNBC · Secondary source · 2026-10-06 · Body (retrieved 2026-11-07)
- [3]
Utility Dive reported that on June 18, 2026 FERC issued six show cause orders finding grid operators' large-load interconnection rules appeared inadequate, naming five issues including cost shifts, co-location and services for flexible loads. reportedas of 2026-06-22
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · First paragraph (retrieved 2026-11-07)
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body (retrieved 2026-11-07)
- [4]
On August 3, 2026 Texas Governor Greg Abbott called for an audit of all data centres in ERCOT's interconnection queue, pausing new connections; he said queue requests totalled about 474 GW, more than five times ERCOT's record peak, and about 90% were data centres. reportedas of 2026-08-05
- Texas hits pause on data center interconnections · Utility Dive · Secondary source · 2026-08-05 · Dive Brief (retrieved 2026-11-07)
- Texas hits pause on data center interconnections · Utility Dive · Secondary source · 2026-08-05 · Dive Brief (retrieved 2026-11-07)
- [5]
ERCOT said in August 2026 that it aimed to audit hundreds of data centre proposals by December 10, a step needed before large-load connections can resume; about 300 data centres of 75 MW or more are in its Batch Zero study process. reportedas of 2026-08-21
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: ERCOT aims to complete Texas governor's data center audit by December (Aug. 21, 2026) (retrieved 2026-11-07)
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: ERCOT aims to complete Texas governor's data center audit by December (Aug. 21, 2026) (retrieved 2026-11-07)
- [6]
The IEA estimates that global electricity demand from data centres grew 17% in 2025, in line with its earlier projections. confirmedas of 2026-04-16
- Key Questions on Energy and AI - Executive summary · International Energy Agency · Primary source · 2026-04-16 · Executive summary, opening section (retrieved 2026-11-07)
- [7]
A Gartner forecast reported in July 2026 projects that global data centre electricity use will reach 565 TWh in 2026, up 26% from 447 TWh in 2025. confirmedas of 2026-07-09· forecast
- Gartner: Data center electricity consumption to grow 26% in 2026 · Network World · Secondary source · 2026-07-07 · First paragraph (retrieved 2026-11-07)
- AI servers will consume more power than all conventional data center hardware combined by 2027, Gartner forecasts · Tom's Hardware · Secondary source · 2026-07-09 · First paragraph (retrieved 2026-11-07)
- [8]
Meta says it pays the full cost of the energy its data centres use so that consumers do not bear those expenses. confirmedas of 2026-01-09
- Meta Announces Nuclear Energy Projects, Unlocking Up to 6.6 GW to Power American Leadership in AI Innovation · Meta · Primary source · 2026-01-09 · Body (retrieved 2026-11-07)
- [9]
Google says the Constellation uprate projects will add 890 MW of firm power to the PJM grid before the end of 2032, and that it has now enabled over 1.5 GW of new US nuclear capacity, including the planned restart of Iowa's Duane Arnold plant with NextEra. confirmedas of 2026-10-06
- Why we're backing America's existing nuclear plants · Google · Primary source · 2026-10-06 · Body (retrieved 2026-11-07)
- Why we're backing America's existing nuclear plants · Google · Primary source · 2026-10-06 · Body (retrieved 2026-11-07)
- Why we're backing America's existing nuclear plants · Google · Primary source · 2026-10-06 · Body (retrieved 2026-11-07)
- [10]
On October 27, 2026 Constellation announced a conditional US Department of Energy loan commitment of up to $5 billion for nuclear uprates, and said its 20-year agreements with Google and Amazon had led it to invest over $7 billion to add about 1,080 MW. confirmedas of 2026-10-27
- Constellation Secures Conditional DOE Loan Commitment of up to $5 Billion to Expand Nuclear Output · Constellation Energy · Primary source · 2026-10-27 · First paragraph (retrieved 2026-11-07)
- Constellation Secures Conditional DOE Loan Commitment of up to $5 Billion to Expand Nuclear Output · Constellation Energy · Primary source · 2026-10-27 · First paragraph (retrieved 2026-11-07)
- [11]
Utility Dive reported that Constellation said on its November 2026 earnings call that it is offering "Peak+" contracts pairing existing nuclear output with batteries, demand response or new generation for large customers, and had signed a first, unnamed customer for a 20-year, 270 MW agreement. reportedas of 2026-11-11
- Constellation pursues hybrid capacity contracts alongside nuclear uprates · Utility Dive · Secondary source · 2026-11-11 · Opening paragraph (retrieved 2026-11-14)
- Constellation pursues hybrid capacity contracts alongside nuclear uprates · Utility Dive · Secondary source · 2026-11-11 · Body (retrieved 2026-11-14)
- Constellation pursues hybrid capacity contracts alongside nuclear uprates · Utility Dive · Secondary source · 2026-11-11 · Body (retrieved 2026-11-14)
- [12]
The IEA says gas turbine orders surged 70% in 2025, exposing chokepoints in energy equipment supply chains. confirmedas of 2026-04-16
- Key Questions on Energy and AI - Executive summary · International Energy Agency · Primary source · 2026-04-16 · Section: In an unstable world, the links between AI and energy security have tightened (retrieved 2026-11-07)
- [13]
The IEA says US developers constrained by slow grid connections are pursuing onsite gas generation, that about one-fifth of tracked projects had started land clearing or construction, and that around 15-27 GW of onsite gas may power data centres by 2030, mostly in the United States. confirmedas of 2026-04-16· forecast
- Key Questions on Energy and AI - Executive summary · International Energy Agency · Primary source · 2026-04-16 · Onsite gas section (retrieved 2026-11-07)
- Key Questions on Energy and AI - Executive summary · International Energy Agency · Primary source · 2026-04-16 · Onsite gas section (retrieved 2026-11-07)
- Key Questions on Energy and AI - Executive summary · International Energy Agency · Primary source · 2026-04-16 · Onsite gas section (retrieved 2026-11-07)
- [14]
On October 28, 2026 GE Vernova said it expected its backlog to exceed $200 billion in the fourth quarter and to end 2026 with at least 130 GW of gas equipment under contract; its chief executive said it continues to develop new solutions for utility and data centre customers to meet growing demand. confirmedas of 2026-10-28
- GE Vernova reports strong third quarter 2026 financial performance · GE Vernova · Primary source · 2026-10-28 · CEO quote (retrieved 2026-11-07)
- GE Vernova reports strong third quarter 2026 financial performance · GE Vernova · Primary source · 2026-10-28 · CEO quote (retrieved 2026-11-07)
- [15]
A 2026 agreement between Google and Xcel Energy includes a 300 MW / 30 GWh Form Energy iron-air battery, described as the largest battery project by energy capacity announced to date. reportedas of 2026-03-04
- World's 'largest' grid battery part of Google-Xcel Energy agreement · Utility Dive · Secondary source · 2026-03-04 (retrieved 2026-10-10)
- [16]
On 24 March 2026 Form Energy and Crusoe announced an agreement for 12 gigawatt-hours of iron-air storage for AI data centers, with deliveries from 2027 built at Form Factory 1 in Weirton, West Virginia. confirmedas of 2026-03-24
- Form Energy and Crusoe announce agreement for 12 gigawatt-hours of iron-air batteries for AI data centers · Crusoe · Primary source · 2026-03-24 · Headline and body (retrieved 2026-10-10)
- [17]
The US Department of Energy directed FERC in October 2025 to set rules for connecting data centres to the transmission system, and the proposal drew more than 3,500 pages of comments. reportedas of 2026-06-22
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body (retrieved 2026-11-07)
- 6 takeaways from FERC's data center interconnection decision · Utility Dive · Secondary source · 2026-06-22 · Body (retrieved 2026-11-07)
- [18]
Utility Dive reported in August 2026 that FERC had extended grid operators' deadline to respond to the show cause orders until mid-November. reportedas of 2026-08-24
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Microsoft, PowerHouse Hillwood dispute data center service agreements (Aug. 24, 2026) (retrieved 2026-11-07)
- [19]
Utility Dive reported that FERC in October 2026 largely rejected PJM's plan for connecting data centers and other large loads, including its Interim Resource Adequacy Service, which would have let large loads connect without matching new capacity if they agreed to be curtailed ahead of grid emergencies, finding that key parts intruded on state jurisdiction over retail rates and appeared to discriminate against large loads; FERC approved PJM's large-load definition and registry. reportedas of 2026-10-12
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Opening paragraph (retrieved 2026-11-14)
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Second paragraph (retrieved 2026-11-14)
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Second paragraph (retrieved 2026-11-14)
- FERC rejects most of PJM's large load interconnection plan · Utility Dive · Secondary source · 2026-10-12 · Body (retrieved 2026-11-14)
- [20]
On May 4, 2026 NERC issued a Level 3 alert, its highest, requiring grid entities to take seven actions by August 3 after data centres unexpectedly dropped load or swung demand rapidly. reportedas of 2026-05-05
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: NERC issues Level 3 alert (May 5, 2026) (retrieved 2026-11-07)
- [21]
On July 9, 2026 the Public Utility Commission of Texas unanimously approved rules requiring large computational loads in ERCOT to stay connected through grid disturbances; ERCOT said it had seen 28 trips of at least 100 MW since 2023. reportedas of 2026-07-13
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Texas PUC approves ride-through rules for data centers (July 13, 2026) (retrieved 2026-11-07)
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Texas PUC approves ride-through rules for data centers (July 13, 2026) (retrieved 2026-11-07)
- [22]
About 3,800 MW of data centre load tripped offline in northern Virginia on July 22, 2026 after a fault on a 230-kV line, the largest such event in PJM's history, according to the grid operator. reportedas of 2026-08-12
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: PJM eyes data center, crypto reliability requirements (Aug. 12, 2026) (retrieved 2026-11-07)
- [23]
Utility Dive reported that New York in July 2026 halted new data centre approvals for up to a year while the state writes new development rules. reportedas of 2026-08-05
- Texas hits pause on data center interconnections · Utility Dive · Secondary source · 2026-08-05 · Dive Insight (retrieved 2026-11-07)
- [24]
On August 18, 2026 Pennsylvania Governor Josh Shapiro signed an executive order giving faster state permitting to data centres over 25 MW that source power from new supplies and accept the state's cost-responsibility standards. reportedas of 2026-08-19
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Pennsylvania dangles permitting carrot (Aug. 19, 2026) (retrieved 2026-11-07)
- [25]
At least 81 US cities and counties had moratoriums on data centre development in August 2026, according to a National League of Cities database. reportedas of 2026-08-19
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Pennsylvania dangles permitting carrot (Aug. 19, 2026) (retrieved 2026-11-07)
- [26]
The Smart Electric Power Alliance counted 77 large-load tariffs pending or in place across 36 US states as of March 2026; state regulators approved 29 in 2025, against 14 from 2018 to 2024. reportedas of 2026-03-31
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Large load tariffs proliferate (March 31, 2026) (retrieved 2026-11-07)
- Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: Large load tariffs proliferate (March 31, 2026) (retrieved 2026-11-07)
- [27]
In its October 2026 Short-Term Energy Outlook, the EIA forecast 2026 wholesale electricity prices in the PJM region 41% higher than in 2025, the largest increase of any region it tracks. confirmedas of 2026-10-06· forecast
- Short-Term Energy Outlook, October 2026 - Electricity, coal, and renewables · US Energy Information Administration · Primary source · 2026-10-06 · Electricity prices and consumption (retrieved 2026-11-07)
- [28]
The IEA's April 2026 projection has data centre electricity use roughly doubling from 485 TWh in 2025 to 950 TWh in 2030, about 3% of global electricity demand. confirmedas of 2026-04-16· forecast
- Key Questions on Energy and AI - Executive summary · International Energy Agency · Primary source · 2026-04-16 · Section: Our updated data centre electricity demand outlook (retrieved 2026-11-07)
Revision history (2)
Created Nov 7, 2026. Last reviewed by an editor on Nov 8, 2026. Next scheduled review: Nov 23, 2026.