    ERCOT, the Electric Reliability Council of Texas, manages the flow of electric power to more than 27 million Texas customers, about 90% of the state's electric load, and is overseen by the Public Utility Commission of Texas and the Texas Legislature.[1][2] Its grid has few links to the rest of the country, a feature that drew attention when generation fell below forecast demand in the February 2021 winter storm.[3][4]

    Editor reviewedUpdated Wiki18 claims · 83% primaryEnergy and climate, Economy and trade
    Key facts

    ERCOT, the Electric Reliability Council of Texas, runs the grid that serves more than 27 million Texas customers, about 90% of the state’s electric load.[1] It is unusual among US grid operators because its system is largely cut off from the rest of the country, and it is now handling a surge of requests from data centres.[3][5]

    What ERCOT does

    As the independent system operator for its region, ERCOT schedules power on a grid of more than 55,000 miles of transmission lines and more than 1,460 generation units.[1] It also settles the competitive wholesale bulk-power market and administers retail switching for nearly 8 million premises in areas where customers can choose their electricity provider.[6] Its grid covers about 75% of the land area of Texas.[7]

    ERCOT is a membership-based 501(c)(4) nonprofit corporation governed by a board of directors and overseen by the Public Utility Commission of Texas and the Texas Legislature.[2] It became the first independent system operator in the US in 1996, when it was reorganized from a reliability council.[8]

    Why the Texas grid stands apart

    The lower 48 states have three big grids, called interconnections: Eastern, Western and ERCOT. They mostly run on their own and rarely trade electricity.[9] ERCOT covers most, but not all, of Texas,[10] and it has few connections to grids outside the state.[3]

    ERCOT is the only US system in which the balancing authority, the interconnection and the regional transmission organization are the same entity and physical system.[10] Its network is tightly controlled, with few ties to grids outside the state, and it received little power from outside the region during the February 2021 disruption.[3] Elsewhere, such as pjm-interconnection, RTOs span many states and their grids are part of a much larger interconnection.[11]

    The February 2021 winter storm

    In mid-February 2021 extreme cold disrupted energy supply in Texas. The EIA reported that freezing temperatures disrupted natural gas production and that pipeline compressors lost power. Gas-fired generation fell sharply once rotating outages began at midnight on 15 February, and output from coal plants, a nuclear plant and wind farms also fell around then.[12] ERCOT’s generation fell below its day-ahead forecast demand from shortly after midnight on 15 February through 18 February. The gap between actual demand and the day-ahead forecast reached at least 30,000 MW on 15 February.[4] ERCOT received little power from outside its region during the crisis.[3]

    The Federal Reserve Bank of Dallas reported that nearly 4 million Texas customers, more than 11 million people, lost power. It said the outages caused at least 111 deaths, and early estimates put the economic loss at $80 billion to $130 billion.[13]

    Fuel mix and records

    ERCOT’s operational installed capacity for summer 2026 was 37.5% natural gas, 22.4% wind, 19.7% solar, 8.6% storage, 7.6% coal and 2.9% nuclear.[14] As of October 2026 it reported 41,208 MW of installed wind, the most of any US state, plus 41,926 MW of utility-scale solar and 21,537 MW of battery storage.[15] Demand set an unofficial record of 91,155 MW on 22 July 2026.[16] For how these technologies work, read how wind power works and how solar power works.

    Data centres and the large-load queue

    In July 2026 the Public Utility Commission of Texas approved rules requiring large computing loads in ERCOT to stay connected through grid disturbances. ERCOT said it had seen 28 trips of at least 100 MW since 2023.[17] In August the governor called for an audit of every data centre in ERCOT’s interconnection queue, pausing new connections. He said queue requests totalled about 474 GW, more than five times ERCOT’s record peak.[5] ERCOT said it aimed to finish auditing the proposals by 10 December, a step needed before large-load connections can resume.[18] The AI data centre power tracker follows the audit.

    ERCOT’s website blocks automated readers, so its company profile and latest fact sheet were read through Internet Archive copies. ERCOT marks its demand records as unofficial until final settlement.

    PJM Interconnection

    PJM runs the grid and wholesale power market for 67 million people in 13 states and DC. Its history, size, capacity auctions and the data centre squeeze.

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    What is ERCOT?

    ERCOT is the independent system operator for most of Texas. It manages the flow of power to more than 27 million customers, about 90% of the state's electric load, schedules power on a grid of more than 55,000 miles of transmission lines, settles the wholesale market and handles retail switching in competitive areas.[1][6]

    Who regulates ERCOT?

    ERCOT is a membership-based 501(c)(4) nonprofit governed by a board of directors and overseen by the Public Utility Commission of Texas and the Texas Legislature.[2]

    Is the Texas grid separate from the rest of the US?

    Largely. The lower 48 states have three main interconnections, Eastern, Western and ERCOT, which mostly operate independently. ERCOT's balancing authority, interconnection and grid operator are the same system, and it has few connections to grids outside Texas.[9][10][3]

    What happened to the Texas grid in February 2021?

    In a severe winter storm, ERCOT's generation fell below day-ahead forecast demand from 15 to 18 February, and the gap between actual and forecast demand reached at least 30,000 MW. Frozen gas wells, compressors without power, and lower output from coal, nuclear and wind plants all played a part. The Dallas Fed reported that nearly 4 million customers lost power and at least 111 people died.[4][12][13]

    What powers the ERCOT grid?

    For summer 2026, ERCOT's operational installed capacity was 37.5% natural gas, 22.4% wind, 19.7% solar, 8.6% storage, 7.6% coal and 2.9% nuclear. It reports more installed wind capacity than any other US state.[14][15]

    Sources

    · 18 claims from 5 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      ERCOT manages the flow of electric power to more than 27 million Texas customers, about 90% of the state's electric load, and schedules power on a grid of more than 55,000 miles of transmission lines and more than 1,460 generation units. confirmedas of 2026-10-16

    2. [2]

      ERCOT is a membership-based 501(c)(4) nonprofit corporation governed by a board of directors and overseen by the Public Utility Commission of Texas and the Texas Legislature. confirmedas of 2026-10-22

    3. [3]

      ERCOT has few connections to grids outside Texas and received little power from outside the region during the February 2021 disruption. confirmedas of 2021-02-19

    4. [4]

      During the February 2021 winter storm, ERCOT's generation fell below its day-ahead forecast demand from shortly after midnight on 15 February through 18 February, and the gap between actual demand and day-ahead forecast demand reached at least 30,000 MW on 15 February. confirmedas of 2021-02-19

    5. [5]

      On August 3, 2026 Texas Governor Greg Abbott called for an audit of all data centres in ERCOT's interconnection queue, pausing new connections; he said queue requests totalled about 474 GW, more than five times ERCOT's record peak, and about 90% were data centres. reportedas of 2026-08-05

    6. [6]

      ERCOT performs financial settlement for the competitive wholesale bulk-power market and administers retail switching for nearly 8 million premises in competitive choice areas. confirmedas of 2026-10-22

    7. [7]

      The ERCOT grid covers about 75% of the land area of Texas. confirmedas of 2026-10-22

    8. [8]

      ERCOT became the first independent system operator in the US in 1996, when it was reorganized from a reliability council. confirmedas of 2021-02-19

    9. [9]

      The grid in the lower 48 US states has three main interconnections, Eastern, Western and ERCOT (most of Texas), which mostly operate independently and rarely transfer electricity among them. confirmedas of 2026-11-07

    10. [10]

      ERCOT is unusual among US grids in that its balancing authority, interconnection and regional transmission organization are the same entity and physical system, covering most but not all of Texas. confirmedas of 2026-11-07

    11. [11]

      PJM Interconnection is a regional transmission organization that coordinates the movement of wholesale electricity in all or parts of 13 states and the District of Columbia, serving more than 67 million people. confirmedas of 2026-11-07

    12. [12]

      In the February 2021 storm, freezing temperatures disrupted Texas natural gas production and pipeline compressors lost power, while gas, coal, nuclear and wind output in ERCOT all fell around the start of rotating outages. confirmedas of 2021-02-19

    13. [13]

      The Federal Reserve Bank of Dallas reported that nearly 4 million Texas customers, more than 11 million people, lost power in February 2021, that the outages caused at least 111 deaths, and that early estimates put the economic loss at $80 billion to $130 billion. confirmedas of 2021-04-15

    14. [14]

      ERCOT's operational installed capacity for summer 2026 was 37.5% natural gas, 22.4% wind, 19.7% solar, 8.6% storage, 7.6% coal and 2.9% nuclear, based on its December 2025 capacity report. confirmedas of 2026-10-16

      • ERCOT Fact Sheet, October 2026 · Electric Reliability Council of Texas · Primary source · 2026-10-16 · Fact sheet, 2026 Generating Capacity chart: Natural Gas 37.5%, Wind 22.4%, Solar 19.7%, Storage 8.6%, Coal 7.6%, Nuclear 2.9%, Hydro 0.3%, Other 0.1% (retrieved 2026-11-07)
    15. [15]

      As of October 2026 ERCOT reported 41,208 MW of installed wind capacity, the most of any US state, 41,926 MW of utility-scale solar and 21,537 MW of energy storage. confirmedas of 2026-10-16

      • ERCOT Fact Sheet, October 2026 · Electric Reliability Council of Texas · Primary source · 2026-10-16 · Fact sheet: 41,208 MW wind; 41,926 MW utility-scale solar; 21,537 MW energy storage, all as of October 2026 (retrieved 2026-11-07)
    16. [16]

      ERCOT recorded an unofficial record peak demand of 91,155 MW on 22 July 2026. confirmedas of 2026-10-16

      • ERCOT Fact Sheet, October 2026 · Electric Reliability Council of Texas · Primary source · 2026-10-16 · Fact sheet: '91,155 MW Record peak demand (July 22, 2026)' (retrieved 2026-11-07)
    17. [17]

      On July 9, 2026 the Public Utility Commission of Texas unanimously approved rules requiring large computational loads in ERCOT to stay connected through grid disturbances; ERCOT said it had seen 28 trips of at least 100 MW since 2023. reportedas of 2026-07-13

    18. [18]

      ERCOT said in August 2026 that it aimed to audit hundreds of data centre proposals by December 10, a step needed before large-load connections can resume; about 300 data centres of 75 MW or more are in its Batch Zero study process. reportedas of 2026-08-21

      • Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: ERCOT aims to complete Texas governor's data center audit by December (Aug. 21, 2026) (retrieved 2026-11-07)
      • Trendline: Data Centers and the US Grid · Utility Dive · Secondary source · Article: ERCOT aims to complete Texas governor's data center audit by December (Aug. 21, 2026) (retrieved 2026-11-07)
    Revision history (1)
    1. Page created.

    Created Nov 7, 2026. Last reviewed by an editor on Nov 8, 2026. Next scheduled review: Feb 7, 2027.

    Cite this page

    "ERCOT (Electric Reliability Council of Texas)." ContentLora, updated Nov 7, 2026. https://contentlora.com/wiki/ercot

    Spotted an error? Suggest a correction or emailcorrections@contentlora.com.