    SMR projects tracker: 2025-26 licences, contracts and construction

    By 7 November 2026 the NRC had issued construction permits for TerraPower's Natrium plant in Wyoming and TVA's BWRX-300 at Clinch River, and finished its safety review of X-energy's Long Mott plant in Texas.[1][2][3] Canada's Darlington BWRX-300, under construction since 2025, applied for an operating licence in March 2026, and the UK signed a contract for three Rolls-Royce SMRs at Wylfa in April.[4][5][6]

    Editor reviewedUpdated Developing28 claims · 25% primary21 entries · last entry Next check Dec 1, 2026Energy and climate, Physics

    What we know

    • Darlington's first BWRX-300 has had a construction licence since April 2025 and applied for an operating licence on March 25, 2026[5]
    • The NRC issued a construction permit for the Natrium plant at Kemmerer, Wyoming, on 5 March 2026[1]
    • The NRC issued TVA a construction permit for a BWRX-300 at Clinch River on 30 September 2026[2]
    • The NRC released its final safety evaluation for Long Mott (four Xe-100s) on 30 October 2026[3]
    • Rolls-Royce SMR and GBE-N signed a contract for three units at Wylfa on 13 April 2026[6]
    • No grid connection of Linglong One had been reported as of 3 November 2026[22]

    What we don't know yet

    • When the NRC will issue the Long Mott construction permit, which it said would be announced soon
    • When the CNSC will hold the public hearing on Darlington's operating licence
    • When Linglong One will connect to the grid and enter commercial operation
    • When TVA will start building at Clinch River, and how cost sharing with partners will be settled
    • What the first Western SMRs will actually cost once built

    Small modular reactor projects gained key approvals in 2025 and 2026. The US regulator approved construction of two plants and finished reviewing a third, while Canada’s first unit is being built.[1][2][3][4] The leading Western projects target the end of the decade: Darlington plans its first grid connection by the end of 2030, and TerraPower expects to complete Kemmerer Unit 1 in 2030.[7][8]

    This tracker follows licensing, funding, contract and construction milestones for small modular reactors and related advanced reactors. It is updated as regulators and developers announce new steps. For background, read small modular reactors explained first. Power deals for data centers are tracked in the AI data center power tracker.

    Canada: Darlington

    Ontario Power Generation received a CNSC licence in April 2025 to build one BWRX-300 at Darlington, the first of four planned units.[4] Ontario approved a CAD20.9 billion budget the following month and plans to connect the first unit to the grid by the end of 2030.[7] The CNSC lifted the first regulatory hold point, for the reactor building foundation, on March 30, 2026.[9] OPG had applied on March 25 for a 20-year operating licence, which will be decided after a public hearing not yet scheduled.[5] World Nuclear News reported that the unit looks set to be the first SMR in a G7 country.[10]

    United States: permits and funding

    The NRC approved TerraPower’s construction permit for the 345 MWe Natrium plant at Kemmerer, Wyoming, on 5 March 2026, after an 18-month review.[1][11] TerraPower officially started construction in April and expects to finish in 2030.[8] On 30 September the NRC issued TVA a construction permit for a BWRX-300 at Clinch River, Tennessee; TVA has not set a construction date.[2] On 30 October the NRC released its final safety evaluation for Long Mott, four Xe-100 units at Dow’s Seadrift site in Texas, and said a construction permit announcement would come soon.[3] Holtec’s application for two SMR-300s at Palisades, Michigan, was accepted for review in February 2026.[12] Kairos Power broke ground on its two-unit Hermes 2 demonstration in April 2026.[13]

    Federal money backs several of these projects. In December 2025 the DOE picked TVA and Holtec for USD400 million each.[14] In May 2026 it awarded more than $94 million to eight companies for licensing, supply chain and site work, including early site permits in New York and Nebraska.[15] X-energy said in August that the DOE would add $1 billion for Long Mott.[16]

    United Kingdom and Europe

    The UK chose Rolls-Royce SMR in June 2025 and confirmed Wylfa on Anglesey as the site in November 2025.[17][18] Rolls-Royce SMR and Great British Energy - Nuclear signed the delivery contract for three units on 13 April 2026.[6] Rolls-Royce SMR also has a commitment for up to six units in Czechia.[19] In Sweden, Blykalla applied in May 2026 to build a 330 MWe plant of six lead-cooled SEALER reactors at Norrsundet, Gävle.[20]

    China: Linglong One

    China’s Linglong One, a 125 MWe ACP100, completed cold functional tests in October 2025 and its steam turbine test in December 2025.[21][22] The World Nuclear Association’s 3 November 2026 update still listed commissioning as expected during 2026, with no grid connection recorded.[22]

    Big-tech buyers

    Google signed a deal with Kairos Power in 2024 for up to 500 MW from multiple SMRs by 2035.[23] Amazon’s collaboration with X-energy, launched in 2024, aims to deploy 5 GW of new capacity by 2039.[24] Its first project is Energy Northwest’s Cascade facility in Washington, where X-energy hired Fluor for engineering on 6 November 2026.[25] In October 2026 American Electric Power and X-energy agreed to evaluate a 960 MWe second project at a former coal plant site in Indiana.[26]

    Timeline

    19 confirmed2 reported

    1. confirmed

      X-energy picks Fluor for its second Xe-100 project, at Cascade in Washington[25]

    2. confirmed

      NRC completes Long Mott safety review[3]

    3. confirmed

      AEP and X-energy agree to study a 960 MWe Xe-100 plant in Indiana[26]

      The source gives October 2026 without a day.

    4. confirmed

      NRC issues construction permit for TVA's Clinch River BWRX-300[2]

      The review took 14 months, four months less than scheduled.

    5. reported

      X-energy says DOE will add $1 billion for Long Mott[16]

      The source gives August 2026 without a day. Federal support would total about $2.15 billion.

    6. confirmed

      Blykalla applies to build six SEALER reactors at Norrsundet, Sweden[20]

    7. confirmed

      DOE awards more than $94 million to eight light-water SMR suppliers and sites[15]

    8. confirmed

      NRC finds no significant environmental impact for Long Mott[28]

      The source gives May 2026 without a day.

    9. confirmed

      TerraPower officially starts building Kemmerer Unit 1[8]

    10. confirmed

      Contract signed for three Rolls-Royce SMRs at Wylfa[6][19]

      The National Wealth Fund committed up to GBP599 million to Rolls-Royce SMR.

    11. confirmed

      Kairos breaks ground on Hermes 2 in Tennessee[13]

      The source gives April 2026 without a day.

    12. confirmed

      CNSC lifts first Darlington hold point, for the reactor building foundation[9]

    13. confirmed

      OPG applies for an operating licence for the first Darlington BWRX-300[5]

    14. confirmed

      NRC approves Natrium construction permit at Kemmerer, Wyoming[1]

      World Nuclear News called it the first US permit for a commercial-scale non-light-water reactor in four decades.

    15. confirmed

      NRC accepts Holtec's Palisades SMR-300 application for review[12]

      The source gives February 2026 without a day.

    16. confirmed

      DOE awards USD400 million each to TVA and Holtec[14]

      The funds support a BWRX-300 at Clinch River and two SMR-300s at Palisades, Michigan.

    17. reported

      Linglong One completes its steam turbine test[22]

      The World Nuclear Association dates the test to December 2025 without a day, with commissioning expected during 2026.

    18. confirmed

      UK confirms Wylfa on Anglesey for its first SMRs[18]

      The government expects power from the mid-2030s.

    19. confirmed

      UK picks Rolls-Royce SMR after a two-year competition[17]

    20. confirmed

      NuScale's 77 MWe US460 design gets NRC standard design approval[27]

      The source gives May 2025 without a day.

    21. confirmed

      Canada licenses construction of the first Darlington BWRX-300[4]

      The CNSC licence covers one of four planned units at Ontario Power Generation's Darlington site.

    How nuclear fission reactors work

    How fission reactors make electricity: chain reactions, moderators, coolants, PWR, BWR, CANDU and Gen IV designs, LEU and HALEU fuel, waste and safety.

    More in Energy and climate

    Developing in Science & Energy

    Go deeper

    Questions readers ask

    Has the NRC approved any SMR construction in 2026?

    Yes. It issued construction permits for TerraPower's Natrium plant in Wyoming on 5 March 2026 and for TVA's BWRX-300 at Clinch River, Tennessee, on 30 September 2026.[1][2]

    Which NRC review finished most recently?

    The safety review of Long Mott, a four-unit Xe-100 plant in Texas, finished on 30 October 2026. The NRC said a construction permit announcement would come soon.[3]

    When will Darlington's SMR start up?

    OPG applied for an operating licence in March 2026, and the CNSC will decide after a public hearing that has not been scheduled. The plan is to connect the first unit to the grid by the end of 2030.[5][7]

    Is China's Linglong One running?

    No grid connection had been reported as of 3 November 2026. Its steam turbine test was completed in December 2025, with commissioning expected during 2026.[22]

    Where will the UK build its first SMRs?

    At Wylfa on Anglesey, North Wales. A contract for three Rolls-Royce SMRs was signed in April 2026, with power expected from the mid-2030s.[18][6]

    Sources

    · 28 claims from 7 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      On 5 March 2026 the NRC approved a construction permit for TerraPower's Kemmerer Unit 1 Natrium plant in Wyoming, the first for a commercial-scale non-light-water reactor in about four decades, after an 18-month review against an initial 27-month schedule. reportedas of 2026-03-05

    2. [2]

      On 30 September 2026 the NRC issued TVA a construction permit for a BWRX-300 at Clinch River, Tennessee, completing its review in 14 months, four months ahead of schedule; TVA has not announced a construction date. reportedas of 2026-09-30

    3. [3]

      On 30 October 2026 the NRC released its final safety evaluation for the Long Mott Generating Station in Texas, four Xe-100 reactors totalling 320 MWe for Dow's Seadrift site, and said a construction permit announcement would come soon. reportedas of 2026-11-07

    4. [4]

      In April 2025 the Canadian Nuclear Safety Commission issued Ontario Power Generation a licence to construct one BWRX-300 reactor at the Darlington New Nuclear Project. confirmedas of 2026-11-07

    5. [5]

      On March 25, 2026 OPG applied for a 20-year licence to operate the first Darlington BWRX-300; the CNSC will decide after a public hearing whose date has not been announced. confirmedas of 2026-11-07

    6. [6]

      On 13 April 2026 Rolls-Royce SMR and Great British Energy - Nuclear signed a contract to start delivering three Rolls-Royce SMRs at Wylfa, and the National Wealth Fund committed up to GBP599 million to Rolls-Royce SMR. reportedas of 2026-04-13

    7. [7]

      In May 2025 Ontario approved a CAD20.9 billion (USD15 billion) budget for the Darlington project and the start of construction of the first of four planned BWRX-300s, with grid connection of the first unit planned by the end of 2030. reportedas of 2026-04-02

    8. [8]

      TerraPower announced the official start of construction of Kemmerer Unit 1 in April 2026 and expects the project to be complete in 2030. reportedas of 2026-04-23

    9. [9]

      The CNSC lifted the first regulatory hold point on the Darlington construction licence, for the reactor building foundation, on March 30, 2026. confirmedas of 2026-11-07

    10. [10]

      World Nuclear News reported that the Darlington BWRX-300 looks set to be the first SMR in a G7 country. reportedas of 2026-04-02

    11. [11]

      TerraPower's Natrium is a 345 MWe sodium-cooled fast reactor with molten-salt energy storage that lets the plant boost output to 500 MWe when needed. reportedas of 2026-03-05

    12. [12]

      Holtec submitted a partial construction permit application for two SMR-300s at Palisades in December 2025; it was accepted for review in February 2026. reportedas of 2026-11-04

    13. [13]

      The NRC issued Kairos Power a construction permit for the 35 MWt Hermes test reactor in December 2023 and permits for the two-unit Hermes 2 facility in November 2024; Hermes 2 broke ground in April 2026. reportedas of 2026-11-04

    14. [14]

      On 3 December 2025 the DOE selected the Tennessee Valley Authority (for a BWRX-300 at Clinch River) and Holtec (for SMR-300s at Palisades, Michigan) to receive USD400 million each in cost-shared funding. reportedas of 2025-12-03

    15. [15]

      On 14 May 2026 the DOE selected eight companies to share more than $94 million in cost-shared funding for light-water SMR licensing, supply chain and site preparation, including early site permit work by Constellation in New York and Nebraska Public Power District. confirmedas of 2026-05-14

    16. [16]

      X-energy said in August 2026 that the DOE would provide a further $1 billion in cost-shared funding for Long Mott, bringing federal support to about $2.15 billion. reportedas of 2026-11-04

    17. [17]

      In June 2025, after a two-year competition, the UK selected Rolls-Royce SMR as preferred bidder to build its first small modular reactors. reportedas of 2025-06-10

    18. [18]

      On 13 November 2025 the UK government confirmed Wylfa on Anglesey, North Wales, as the site of its first SMR power station, with power expected from the mid-2030s. confirmedas of 2025-11-13

    19. [19]

      Rolls-Royce SMR says it has commitments for an initial three units at Wylfa and up to six units in Czechia. reportedas of 2026-04-13

    20. [20]

      In May 2026 Swedish developer Blykalla applied to the government to build a 330 MWe plant of six lead-cooled SEALER reactors at Norrsundet, Gävle. reportedas of 2026-05-18

    21. [21]

      China's ACP100 (Linglong One) is a 125 MWe integral pressurised water reactor with passive cooling for decay heat removal, which CNNC says could supply electricity, heat and desalination. reportedas of 2026-11-03

    22. [22]

      As of the World Nuclear Association's 3 November 2026 update, the latest Linglong One milestones listed were cold functional tests in October 2025 and a steam turbine test in December 2025, with commissioning expected during 2026; no grid connection was listed. reportedas of 2026-11-03

    23. [23]

      In October 2024 Google signed what it called the first corporate agreement to buy nuclear energy from multiple SMRs, with Kairos Power, aiming for a first reactor by 2030 and up to 500 MW by 2035. confirmedas of 2024-10-14

    24. [24]

      In October 2024 Amazon announced an investment in X-energy, including manufacturing capacity to support more than 5 GW of projects using X-energy's technology, starting with an Energy Northwest project in Washington state. confirmedas of 2024-10-16

    25. [25]

      On 6 November 2026 X-energy selected Fluor for engineering on its second Xe-100 project, Energy Northwest's Cascade Advanced Energy Facility near Richland, Washington, the first project under its partnership with Amazon. reportedas of 2026-11-06

    26. [26]

      In October 2026 American Electric Power and X-energy signed a joint development agreement to evaluate a 960 MWe Xe-100 project at a former coal plant site in Indiana. reportedas of 2026-11-06

    27. [27]

      NuScale's US460 design, which received NRC standard design approval in May 2025, uses 77 MWe modules, each with core, pressurizer and steam generators inside one reactor vessel; its VOYGR plants range from 308 MWe (four modules) to 924 MWe (twelve). reportedas of 2026-11-04

    28. [28]

      The NRC completed its environmental review of Long Mott in May 2026 with a finding of no significant impact. reportedas of 2026-11-02

    Revision history (1)
    1. Page created with milestones from April 2025 to 7 November 2026.

    Created Nov 7, 2026. Last reviewed by an editor on Nov 8, 2026. Next scheduled review: Dec 1, 2026.