On February 27, 2026 NASA turned Artemis III from the first Moon landing into a 2027 crewed mission in low Earth orbit to test rendezvous and docking with commercial lunar landers, moving the first landing to Artemis IV in 2028.[1] NASA's October 2026 plan is a roughly 14-day flight in which Orion docks first with a Blue Origin Blue Moon test article and then with a SpaceX Starship test article, which the crew will not enter.[2]
What changed
Artemis III was originally to be the first crewed Moon landing of the Artemis programme. On February 27, 2026 NASA made it a 2027 mission in low Earth orbit to test systems and operations with one or both commercial lunar landers, ahead of a first landing on Artemis IV in 2028.[1] In the same update NASA said it would keep the SLS rocket close to its current Block 1 configuration and aim for at least one surface landing a year after that.[3] NASA describes Artemis IV as the first planned crewed mission to the lunar South Pole.[4]
The crew
On June 9, 2026 NASA named the crew: Randy Bresnik (commander), ESA astronaut Luca Parmitano (pilot), Andre Douglas and Frank Rubio.[5] They follow the four astronauts who flew around the Moon on Artemis II in April 2026.[6]
How the mission is meant to work
NASA set out the mission in detail on October 23, 2026 as a planned 14-day flight in Earth orbit.[2] Blue Origin goes first, launching a Blue Moon Mark 2 lander test article into a circular orbit about 273 miles up, where it can wait for up to 30 days. Orion and its crew then launch on SLS from Kennedy Space Center days later.[7] After docking, the astronauts are to spend about two days aboard Blue Moon, opening the hatch to assess its cabin, controls and life support.[8]
Orion then undocks, and SpaceX launches a Version 3 Starship lander test article for a second docking. The crew will not enter Starship.[2] That test is expected to last up to two hours and checks how Orion and Starship behave as a docked system. Orion uses a port beside Blue Moon’s cabin but docks nose to nose with Starship.[9] Afterwards the crew has up to five more days in orbit for other tests before splashing down in the Pacific off California.[10]
The landers and the 2028 landing
In the same October 2026 update NASA said both SpaceX and Blue Origin are aiming to be able to support a crewed landing in 2028.[11] It realigned both contracts so that neither provider is assigned to a specific landing mission, and said it will decide based on readiness which company lands astronauts first in 2028.[12] Orion and the landers will no longer meet in a near-rectilinear halo orbit around the Moon. Each provider will use its own orbit instead.[13] For SpaceX’s lander, see spacex-starship.
Where the hardware stands
In late October 2026 NASA joined the Artemis III SLS core stage to its twin solid rocket boosters in the Vehicle Assembly Building at Kennedy Space Center. The next step is a tanking test at Launch Pad 39B.[14] Later milestones are tracked on the space exploration tracker.
Read next
Artemis program
NASA's Artemis program aims to return astronauts to the Moon. Artemis II flew in April 2026; the first landing is now planned for Artemis IV in 2028.
More in Space exploration
Questions readers ask
Will Artemis III land on the Moon?
No. Since NASA's February 2026 restructuring, Artemis III is a 2027 crewed mission in low Earth orbit to test rendezvous and docking with commercial landers. The first landing is planned for Artemis IV in 2028.[1]
Who is on the Artemis III crew?
NASA named Randy Bresnik (commander), ESA astronaut Luca Parmitano (pilot), Andre Douglas and Frank Rubio on June 9, 2026.[5]
What will Artemis III actually do?
In NASA's October 2026 plan, Blue Origin launches a Blue Moon lander test article, Orion launches on SLS and docks with it, then SpaceX launches a Starship test article for a second docking. The crew is to spend about two days aboard Blue Moon but will not enter Starship.[2][8]
How long will the mission last?
NASA describes a planned 14-day mission in Earth orbit, ending with a splashdown in the Pacific off California.[2][10]
Which company will land astronauts first?
NASA had not decided as of October 2026. It realigned both lander contracts so that neither company is assigned to a specific landing, and said it will choose based on lander readiness which one lands first in 2028.[12]
Sources
· 14 claims from 1 publisher
Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.
- [1]
On February 27, 2026, NASA changed Artemis III into a 2027 crewed mission in low Earth orbit to test rendezvous and docking with one or both commercial lunar landers, ahead of a first landing on Artemis IV in 2028. confirmedas of 2026-02-27
- NASA Adds Mission to Artemis Lunar Program, Updates Architecture (Release 26-022) · NASA · Primary source · 2026-02-27 (retrieved 2026-10-10)
- [2]
In an October 23, 2026 update, NASA laid out Artemis III as a planned 14-day crewed mission in Earth orbit in 2027, in which Blue Origin launches a Blue Moon lander test article, Orion launches on SLS and docks with it, then SpaceX launches a Version 3 Starship test article for a second docking, which the crew will not enter. confirmedas of 2026-11-04
- NASA Shares Plans to Accelerate Artemis Return to Moon · NASA · Primary source · 2026-11-04 (retrieved 2026-11-07)
- NASA Shares Plans to Accelerate Artemis Return to Moon · NASA · Primary source · 2026-11-04 (retrieved 2026-11-07)
- NASA Shares Plans to Accelerate Artemis Return to Moon · NASA · Primary source · 2026-11-04 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- [3]
In its February 2026 update NASA said it would standardize the SLS rocket on its current Block 1 configuration rather than develop evolved variants, and aim for at least one lunar surface landing every year after Artemis IV. confirmedas of 2026-02-27
- NASA Adds Mission to Artemis Lunar Program, Updates Architecture (Release 26-022) · NASA · Primary source · 2026-02-27 (retrieved 2026-10-10)
- NASA Adds Mission to Artemis Lunar Program, Updates Architecture (Release 26-022) · NASA · Primary source · 2026-02-27 (retrieved 2026-10-10)
- [4]
NASA describes Artemis IV as the first planned crewed mission to the lunar South Pole, targeted for 2028. confirmedas of 2026-06-09
- NASA Marches Toward Artemis III Mission in 2027, Names Crew Members · NASA · Primary source · 2026-06-09 (retrieved 2026-10-10)
- Artemis III mission page · NASA · Primary source (retrieved 2026-10-10)
- [5]
On June 9, 2026, NASA named the Artemis III crew as Randy Bresnik (commander), ESA astronaut Luca Parmitano (pilot), Andre Douglas and Frank Rubio, for a roughly two-week mission in low Earth orbit in 2027. confirmedas of 2026-06-09
- NASA Marches Toward Artemis III Mission in 2027, Names Crew Members · NASA · Primary source · 2026-06-09 (retrieved 2026-10-10)
- [6]
Artemis II launched from NASA's Kennedy Space Center on April 1, 2026, and splashed down on April 10, 2026, after a mission of 9 days, 1 hour and 32 minutes. confirmedas of 2026-10-10
- Artemis II mission page · NASA · Primary source (retrieved 2026-10-10)
- [7]
NASA's October 2026 plan has Blue Origin launch a Blue Moon Mark 2 lander test article into a circular low Earth orbit about 273 miles up, where it can stay for up to 30 days; Orion is to launch on SLS from Kennedy Space Center days later. confirmedas of 2026-10-23
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- [8]
NASA plans for the Artemis III astronauts to spend about two days aboard the docked Blue Moon test article, entering it to assess the cabin, controls and life-support systems. confirmedas of 2026-10-23
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- [9]
Under NASA's plan, the Starship docking test on Artemis III is expected to last up to two hours and focuses on how Orion and Starship behave as a docked system; Orion will use different docking geometries with the two landers. confirmedas of 2026-10-23
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- [10]
NASA says that after the Starship test the Artemis III crew will have up to five more days in orbit for other test objectives before splashing down in the Pacific Ocean off California. confirmedas of 2026-10-23
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- NASA's Artemis III Mission to Test Future Moon Lander Operations · NASA · Primary source · 2026-10-23 (retrieved 2026-11-07)
- [11]
NASA said in its October 2026 Artemis update that both SpaceX and Blue Origin are targeting being able to support a crewed lunar landing in 2028, and that Axiom Space will develop a second, lighter "Sortie" spacesuit for the first moonwalks. confirmedas of 2026-11-04
- NASA Shares Plans to Accelerate Artemis Return to Moon · NASA · Primary source · 2026-11-04 (retrieved 2026-11-07)
- NASA Shares Plans to Accelerate Artemis Return to Moon · NASA · Primary source · 2026-11-04 (retrieved 2026-11-07)
- [12]
On October 23, 2026 NASA said it had realigned its lander contracts so that both SpaceX and Blue Origin take part in Artemis III in low Earth orbit and neither is assigned to a specific landing mission; based on lander readiness, NASA will choose which company lands astronauts first in 2028, with a second crewed landing opportunity to follow. confirmedas of 2026-11-14
- NASA, Partners Accelerate Lander Development for 2028 Moon Missions · NASA · Primary source · 2026-10-23 (retrieved 2026-11-14)
- NASA, Partners Accelerate Lander Development for 2028 Moon Missions · NASA · Primary source · 2026-10-23 · Followed by: 'A second crewed landing opportunity will follow.' (retrieved 2026-11-14)
- [13]
NASA said in October 2026 that, to speed up a 2028 landing, Orion and the landers will no longer meet in a near-rectilinear halo orbit around the Moon but in an orbit that differs for each provider. confirmedas of 2026-11-14
- NASA, Partners Accelerate Lander Development for 2028 Moon Missions · NASA · Primary source · 2026-10-23 (retrieved 2026-11-14)
- [14]
In late October 2026 NASA integrated the Artemis III SLS core stage with its twin solid rocket boosters in the Vehicle Assembly Building at Kennedy Space Center; the stack is next due to roll to Launch Pad 39B for a tanking test. confirmedas of 2026-11-14
- Artemis III SLS Core Stage Joins Boosters at Kennedy · NASA · Primary source · 2026-10-28 · Image article, October 28, 2026 (retrieved 2026-11-14)
- Artemis III SLS Core Stage Joins Boosters at Kennedy · NASA · Primary source · 2026-10-28 (retrieved 2026-11-14)
Revision history (1)
- Page created.
Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: May 14, 2027.
Cite this page
"The new Artemis III plan for 2027." ContentLora, updated Nov 14, 2026. https://contentlora.com/explain/artemis-iii-2027-plan
Spotted an error? Suggest a correction or emailcorrections@contentlora.com.