    SPARC is a compact tokamak that Commonwealth Fusion Systems (CFS) is building in Devens, Massachusetts, to be the first commercially relevant machine to show net fusion energy (Q>1).[1] In November 2026 CFS said it was assembling SPARC and expected to turn it on in 2027, the year it targets for Q>1.[2][3]

    Editor reviewedUpdated Wiki15 claims · 93% primaryFusion energy, Energy and climate, Physics
    Key facts

    SPARC is the fusion machine that commonwealth-fusion-systems is building in Devens, Massachusetts. CFS says it will be the first commercially relevant machine to demonstrate net fusion energy, a result known as Q>1.[1] CFS says data from SPARC will reduce uncertainty in the physics of its planned power plant.[4]

    Design

    SPARC is a tokamak, a donut-shaped machine that uses very strong magnets to hold a plasma at about 100 million degrees Celsius. CFS says its magnets are designed for a top field of 12.2 tesla.[5]

    Those magnets use REBCO high-temperature superconductor. Between 2018 and 2021, MIT’s Plasma Science and Fusion Center and CFS built the SPARC Toroidal Field Model Coil to develop the technology.[6] On 5 September 2021 that coil reached 20 tesla, the strongest fusion magnet of its kind.[7] MIT said magnets like it let a machine match the performance of a conventional device about 40 times larger in volume.[8] More on the technology is in hts-fusion-magnets.

    The Q>1 goal

    Q>1 means a machine has produced more fusion power than was put in to sustain the process. CFS notes that only the national-ignition-facility has done so.[9] CFS publicly targets 2027 for SPARC to reach that threshold.[3] It says SPARC is designed to reach Q>10, so Q>1 is not an extremely difficult milestone.[10]

    CFS describes more than one route. SPARC could reach Q>1 at its full 12.2-tesla field in low-confinement mode (L-mode), or in high-confinement mode (H-mode) at 8 to 9 tesla. After Q>1 in its first campaign, CFS plans to push towards much higher gain.[11]

    Status and timeline

    DateMilestone
    5 Sept 2021SPARC model coil reaches 20 tesla[7]
    6 Jan 2026CFS announces a SPARC digital twin with NVIDIA and Siemens[12]
    5 Aug 2026CFS says SPARC is almost 80% complete[13]
    8 Oct 2026DOE selects CFS for a Genesis Mission project on an AI digital twin for SPARC operations[14]
    2 Nov 2026CFS says it is assembling SPARC and expects to turn it on in 2027[2]

    The build percentage and the 2027 dates come from CFS itself.[13][2] The fusion energy tracker follows SPARC alongside other projects.

    What comes after SPARC

    CFS plans ARC, a power plant of about 400 megawatts at the James River Industrial Center in Chesterfield County, Virginia, expected to supply the grid in the early 2030s.[15] Its June 2026 physics papers for ARC identified areas where data from SPARC will reduce uncertainty.[4] For the international tokamak project, see iter.

    Commonwealth Fusion Systems

    Commonwealth Fusion Systems is building the SPARC tokamak and the ARC power plant around HTS magnets. Its progress, funding and deals as of 2026.

    More in Fusion energy

    Developing in Science & Energy

    Questions readers ask

    What is SPARC?

    A compact tokamak that Commonwealth Fusion Systems is building in Devens, Massachusetts. CFS says it is meant to be the first commercially relevant machine to produce more fusion energy than it needs to run the process, a threshold called Q>1.[1][5]

    When will SPARC start operating?

    In November 2026 CFS said it was assembling the machine and commissioning its support systems, and that it expected to turn SPARC on in 2027. CFS publicly targets 2027 for reaching Q>1.[2][3]

    Has any machine already reached Q>1?

    CFS notes that only one has, the National Ignition Facility at Lawrence Livermore National Laboratory.[9]

    How does SPARC plan to reach Q>1?

    CFS says it has more than one route. It could run at the full 12.2-tesla field in the simpler low-confinement mode, or in high-confinement mode at a lower field of 8 to 9 tesla. After Q>1 it plans to push for higher gain.[11]

    Why are SPARC's magnets important?

    SPARC uses magnets wound from REBCO high-temperature superconductor. A 2021 test magnet built by MIT and CFS for SPARC reached 20 tesla, the strongest fusion magnet of its kind.[6][7]

    Sources

    · 15 claims from 4 publishers

    Each numbered claim is a statement we checked against the sources listed with it. Tap a number in the text to see its sources in place.

    1. [1]

      Commonwealth Fusion Systems says its SPARC tokamak in Devens, Massachusetts, is intended to be the first commercially relevant machine to demonstrate net fusion energy (Q>1). confirmedas of 2026-08-05

    2. [2]

      On 2 November 2026 Commonwealth Fusion Systems said it was assembling SPARC and commissioning its support systems, and its vice president of plasma physics said the company expected to turn SPARC on in 2027. reportedas of 2026-11-02· forecast

    3. [3]

      As of October 2026 Commonwealth Fusion Systems publicly targets 2027 for SPARC to produce more energy from fusion than is needed to power the process, the Q>1 threshold. reportedas of 2026-10-10· forecast

    4. [4]

      On 4 June 2026 CFS published five peer-reviewed physics basis papers for ARC, which it said give confidence that the plant can continuously deliver 400 megawatts of net electricity while identifying physics areas where SPARC data will reduce uncertainty. reportedas of 2026-06-04

    5. [5]

      CFS describes SPARC as a donut-shaped tokamak that uses very strong magnets to hold a plasma at about 100 million degrees Celsius, with magnets designed for a top field of 12.2 tesla. reportedas of 2026-11-02

    6. [6]

      The 20-tesla magnet tested in 2021 was the SPARC Toroidal Field Model Coil, built by MIT's Plasma Science and Fusion Center and CFS between 2018 and 2021 to develop REBCO magnet technology for the SPARC tokamak. reportedas of 2026-10-10

    7. [7]

      On 5 September 2021 MIT and Commonwealth Fusion Systems ramped a large high-temperature superconducting magnet to 20 tesla, the strongest fusion magnet of its kind. confirmedas of 2026-10-10

    8. [8]

      MIT said high-temperature superconducting magnets allow the same performance as a device about 40 times larger in volume built with conventional low-temperature superconducting magnets. confirmedas of 2026-10-10

    9. [9]

      CFS notes that only one machine, the National Ignition Facility at Lawrence Livermore National Laboratory, has produced more fusion energy than was put in to sustain the process (Q>1). reportedas of 2026-11-02

    10. [10]

      In a company blog post current as of October 2026, CFS said it would start operating SPARC "in coming months" and that SPARC is designed to reach Q>10, so Q>1 is not an extremely difficult milestone; CFS has not published a dated first-plasma target. reportedas of 2026-10-10

    11. [11]

      CFS says SPARC could reach Q>1 at its full 12.2-tesla field in low-confinement mode (L-mode), or in high-confinement mode (H-mode) at a lower field of 8 to 9 tesla, and that after Q>1 in its first campaign it plans to push to higher Q. reportedas of 2026-11-02

    12. [12]

      CFS is building a digital twin of SPARC with NVIDIA and Siemens, announced on 6 January 2026, using NVIDIA Omniverse libraries and OpenUSD together with Siemens engineering software. reportedas of 2026-01-06

    13. [13]

      As of 5 August 2026 CFS said SPARC was almost 80 percent complete. reportedas of 2026-08-05

    14. [14]

      On 8 October 2026 CFS said the US Department of Energy had selected it as the only private company leading a project in the second phase of the Genesis Mission, for an AI-enabled digital twin platform to optimise SPARC operations. reportedas of 2026-10-08

    15. [15]

      In December 2024 CFS chose the James River Industrial Center in Chesterfield County, Virginia, for ARC, a planned power plant of about 400 megawatts expected to deliver power to the grid in the early 2030s. confirmedas of 2026-10-10

    Revision history (1)
    1. Page created.

    Created Nov 14, 2026. Last reviewed by an editor on Nov 15, 2026. Next scheduled review: May 14, 2027.

    Cite this page

    "SPARC." ContentLora, updated Nov 14, 2026. https://contentlora.com/wiki/sparc-tokamak

    Spotted an error? Suggest a correction or emailcorrections@contentlora.com.